Batyrzhan Tergessizov, Deputy Chairman of the Management Board for New Projects at QazaqGaz JSC, took part in a production meeting with EPC Contract participants for the construction of the Kashagan Gas Processing Plant, with a capacity of 1 billion cubic meters of gas per year. The meeting addressed the acceleration of construction progress and the timely delivery of equipment.
Current Construction Status:
Over 1,700 personnel are currently engaged at the construction site, including:
-
1,100 direct production workers
-
120 night shift workers
-
300 units of equipment are being utilized for construction and installation activities
Health and Safety Measures:
-
Regular safety audits are being conducted
-
Training sessions are organized to improve qualifications and ensure safe working conditions
Key Work Activities:
-
Installation of metal structures
-
Installation of process equipment
-
Assembly of storage tanks:
-
6 vertical steel tanks (RVS-5000 type)
-
2 vertical steel tanks (RVS-1000 type)
-
10 spherical tanks, each with a capacity of 600 m³
-
-
Piping of technological skids
-
External water supply and sewage system works (NWSS-1 and NWSS-2)
Construction and Installation Progress:
-
Concrete works for foundations at the Gas Processing Unit (GPU): 46,342 m³ completed, 62.1% progress
-
Installation of metal structures: 2,985 tons completed, 14.9% progress
-
Installation of mechanical equipment: 3,142 tons completed, 33.5% progress
-
Tank installation: 544 tons completed, 20.1% progress
-
Underground pipeline installation: 15,787 meters completed, 33.8% progress