Around 2,000 specialists are currently engaged on site, with approximately 155 workers involved in night shifts. Some 360 units of construction machinery are in operation. Particular attention is given to ensuring safe working conditions, including during night hours.
Progress on construction and installation works:
-
Installation of flue stacks has been completed;
-
Ongoing activities include concreting of foundations, installation and painting of steel structures and service platforms, installation and piping of process equipment, as well as assembly of RVS-5000 and 600 m³ spherical storage tanks;
-
Construction of external utility networks (HVK-2) is in progress;
-
At the GPCI camp, roofing has been completed for the administrative and living complex (ALC) and two dormitories accommodating 140 and 132 people. Installation of internal partitions and electrical works are underway in the dormitories and ALC, which form part of the permanent camp infrastructure.
Progress by main work categories:
-
Concrete works for foundations: 54,262 m³ completed (71.5%)
-
Installation of steel structures: 4,328 tonnes (21.4%)
-
Installation of mechanical equipment: 4,326 tonnes (44.6%)
-
Tank installation: 1,187 tonnes (43.9%)
-
Laying of underground pipelines: 20,453 metres (42.1%)
QazaqGaz National Company JSC continues to exercise comprehensive oversight of the project’s implementation, ensuring adherence to construction schedules and compliance with established quality and safety standards at every stage.