At present, more than 1,934 specialists are engaged on site, including 1,347 core personnel. Around 174 workers are involved in night shifts. Over 358 units of construction equipment are in operation. Particular emphasis is placed on ensuring safe working conditions, including during night-time activities.
Progress on construction and installation works:
-
Installation of chimneys has been completed.
-
Ongoing works include concreting of foundations, installation and painting of steel structures and service platforms, installation and tie-in of process equipment, as well as assembly of RVS-5000 storage tanks and spherical tanks with a capacity of 600 m³.
-
Construction of external utility networks (NVK-2) is underway.
-
At the GPCI camp, roofing has been completed on the administrative and amenities complex (AAC) and on two dormitories for 140 and 132 places. Internal partitioning and electrical installation works are in progress within the dormitories and AAC, which form part of the permanent camp infrastructure.
Delivery across the main workstreams:
-
Concrete works for foundations: 53,792 m³ completed (progress 71.1%)
-
Installation of steel structures: 4,193 tonnes (20.7%)
-
Installation of mechanical equipment: 4,320 tonnes (44.6%)
-
Tank installation: 1,187 tonnes (43.9%)
-
Laying of underground pipelines: 19,520 m (48.2%)
JSC "NC QazaqGaz" continues to maintain comprehensive oversight of the project, ensuring adherence to construction deadlines as well as compliance with established quality and safety standards at all stages.