More than 1,300 specialists are currently engaged on site, including 961 direct personnel. A further 101 workers are involved in night shifts. Over 346 units of construction equipment are in operation. Particular attention is being paid to ensuring safe working conditions, including during night-time operations.
Progress on construction and installation works (CIW)
Foundation works, installation of steel structures, service platforms and process facilities are ongoing;
Installation of the firewater pipeline, formwork assembly and foundation reinforcement are in progress, along with backfilling and excavation works for external utility networks (NVK-2);
Installation and painting of steel structures across units and pipe racks continue;
At the shift camp, works are underway on entrance groups, on-site NVK utility networks, electrical installation and low-current systems, as well as partitioning;
Installation of service platforms for gas holders is in progress at Units No. 9 and No. 10. Hydrotesting has been completed on two tanks;
Installation of external wall sandwich panels and partitions is ongoing at Units No. 43, No. 44 and 40/1;
Hydrotesting and repair works of the sulphur pit are underway at Unit No. 7.
Progress across key workstreams:
Concrete works (foundations): 61,032 m³ completed (80.3%)
Steel structure installation: 11,182 tonnes (55.5%)
Mechanical equipment installation: 5,212 tonnes (52.6%)
Tank installation: 1,863 tonnes (92.6%)
Underground pipeline installation: 28,066 m (57.5%)
JSC NC QazaqGaz continues to maintain comprehensive oversight of the project, ensuring adherence to construction timelines as well as compliance with established quality and safety standards at all stages.