About 2,000 specialists are involved at the site. About 170 employees are employed in night shifts. There are about 340 units of construction equipment in operation. Special emphasis is placed on ensuring safe working conditions, including at night. 

Progress on construction and installation works (CMP)

Installation of chimneys is completed; Works on concreting foundations, installation and painting of metal structures and maintenance sites, installation and strapping of technological equipment, as well as the assembly of tanks of types RVS-5000 and spherical tanks with a volume of 600 m3 are carried out.; 

The construction of external engineering networks (NVK-2) is underway. 

In the GPCI shift settlement, roof installation has been completed in the administrative and residential complex (ABC) and in two dormitories with 140 and 132 beds. Internal partitions are being installed and electrical installation works are underway in the buildings of dormitories for 140 and 132 places and ABCs, which are part of the permanent shift camp. Main types of work performed: 

Concrete foundation work: 54,994 m3 completed (72.5% progress) 

Installation of metal structures: 4,865 tons (24%) 

Installation of mechanical equipment: 4,348 tons (44.6%) 

Installation of reservoirs: 1,215 tons (44.9%) 

Laying of underground pipelines: 20,976 m (48.7%) JSC NC QazaqGaz continues comprehensive monitoring of the project implementation, ensuring compliance with construction deadlines, as well as compliance with established quality and safety standards at all stages.